Heads Up for People on Bikes in SE Oly

Saturday, July 8, 2017 Concrete Trucks on Morse-Merryman Road

There will be a large number of concrete trucks on Morse-Merryman Road on Saturday, July 8, 2017.  Trucks may be coming from Boulevard Road or Wiggins Road to access the construction site near LBA Park.  The trucks are involved in pouring concrete for the foundation of the new Log Cabin Road Reservoir. 

This is an all-day activity. Concrete trucks will be running from 5:30 a.m. until about 3:00 p.m. Construction at the site will continue to about 6:00 p.m.

There will be a lot of activity with a lot of large rigs.  Although it may sound exciting, for safety reasons we encourage residents to stay away from the construction site. Use alternate routes when possible.  Please use caution when in the area and be safe out there.

Tim Richardson, Project Manager